SS informed wrong family pictures will be replaced next week. Tilers will also start next week. All cabinets are already installed. Lockup stage completed end of next week and fixing stage completed the week after. We could be in by end of April or early May.
If that's the case, I'd be very happy! Hopefully there will be no major issue from here onwards.
Thursday, March 7, 2013
Thursday, February 14, 2013
14/02 - Bricks delivered
Blackwood was supposed to be burgundy in colour but somehow turn up as chocolate brown!!! Looks more like Homestead Tan. Not sure if I mind about this variation or not.
12/02 - All Wrappped
Brickies was supposed to start this week. However, there might have been delayed in delivery. SS informed that they're planning to start plaster next week. This means plaster up before bricking completed. Our inspector called this Reverse Engineering. It's important to inform builder the intention to perform pre plaster stage inspection otherwise everything would have been covered up. In which, we did.
Monday, February 11, 2013
06/02 - Frame Completed
Our independant inspection was done on this day. It took ~30mins to inspect and would not think more than a couple hours to write the report. What a great business it is. A few minor issues to follow up.
We realised that the standard roof pitch was a bit low for future maintenance, especially lighting is going to be difficult to install. Perhaps worth asking for upgrade with bigger angle for roof pitch.
We realised that the standard roof pitch was a bit low for future maintenance, especially lighting is going to be difficult to install. Perhaps worth asking for upgrade with bigger angle for roof pitch.
Tuesday, January 29, 2013
17/01 - Frame Construction Started
Construction business fully back to normal operation from 14/01/2013 officially and here is what we found on this day:
Monday, December 17, 2012
18/12 - Slab Completed
All this work was done in one day yesterday (17/12/12)
This is what we have today:
Even though still no contact from Site Supervisor. It is still great progress!
Friday, December 7, 2012
03/12 - Site Start (unofficially)
Drove past the house and surprise to find out out site has been scraped. The fence was up the next day.
Our post contract variations after Contract Signing has been extremely slow for only minor changes. Still yet received the latest Post Contract Variations form in almost a month time.
Despite admin slow communications, it is exciting to see something happening on site! We're expecting the Site Supervisor to contact us soon.
DEMOLITION Rectification work for Council Footpath has been very frustrating. Promise after promise .. still not done (a month time). Now the Asset Protection Permit is under our names and we will have to chase both Vic Wide Demolition and MainVue builder AFTER Building Completion (~6-7 months time) for any further damages to council asset before we can get our security bond back. What a hassle !!! Not only that, we already paid in the building contract for the Council Protection Permit.
Our post contract variations after Contract Signing has been extremely slow for only minor changes. Still yet received the latest Post Contract Variations form in almost a month time.
Despite admin slow communications, it is exciting to see something happening on site! We're expecting the Site Supervisor to contact us soon.
DEMOLITION Rectification work for Council Footpath has been very frustrating. Promise after promise .. still not done (a month time). Now the Asset Protection Permit is under our names and we will have to chase both Vic Wide Demolition and MainVue builder AFTER Building Completion (~6-7 months time) for any further damages to council asset before we can get our security bond back. What a hassle !!! Not only that, we already paid in the building contract for the Council Protection Permit.