Monday, August 20, 2012

17/08 - Contract Appointment - Not Signed

Contract Signing has been postponed until after second soil test is done.  This way we can have a more defined site cost as well as slab design ready for council building permit.

As soon as Demolition is completed (which will be by Friday 31/08/12), we'll inform our Admin girl to book second soil test. Results and slab design will take ~2weeks, contract signing will be the week after.  So it's looking at third week of September now to sign contract and site start would be early to mid October.  Hope that there will be no further delays to site start. 

Even if we have signed contract earlier, MainVue would still need to wait for second soil test and slab design. Therefore, it would not make no difference apart from contracting more/less to the provisional lump sum for site costs.  Therefore we decided to wait until all costs refined.

===============================================================


So glad our admin girl who's filling in for the sale consultant is based in Mount Waverley office.  We will be signing up the contract with her in MW, which is much more convenient for us than at Point Cook.  Before tender, we requested to do paperworks at MW.  The sale consultant told us MainVue stopped offering clients to do so as they wanted to separate the business with Henley.   I suppose there's always exception!

No comments:

Post a Comment