Tuesday, August 21, 2012

20/08 - Proposed Demolition Date

Demolition NO GO for next week :( 

Application to AGL for gas abolishment has contained error.  They rang Vic Wide Demo office number and no answer.  They just left it as that without reattempt !!! Now I discovered that our gas meter has not been removed after a month .  Got Vic Wide Demo to ring AGL and found out what was the issue on the form. New form has to be re-submitted.  Now have to wait for another month before demolition can happen !!!

LESSON LEARNED :  Always follow up with a phone call after application submission to make sure everything is correct for processing (even follow-up calls for progress ) ... can't rely on third party to call back ... what a wasteful month of idle !!!

======================================================================

Guaranteed by Sam from Vic Wide Demolition to have job done by Friday 31/07/12.  That is an assurance but we're still behind one week than previously planned.  Hope that they'll do a clean job so that there is no hinderance to site start.

======================================================================

Vic Wide Demolition has been very helpful through out application for demolition.  They're waiting on permit of their Surveyor.  However, they've proposed to our council asset protection permit application that demolition to happen on 20/08, which is on Monday week.  

Cross fingers that it will happen as proposed !!!